A TCEQ 210E authorization in 10 weeks let a 1.0 MGD mixed-use development in San Marcos bypass a discharge permit and its hearings.
1.0 MGD zero-discharge reuse for a mixed-use development

Project
A 2.67-acre office and retail center in Corinth, Texas, won its I-35 frontage driveway approval and was built.
Completed buildings and site work in Corinth, Texas, September 2022.
A 2.67-acre commercial site in Corinth, Texas, was planned for a 10,800 sq ft office building and a 7,316 sq ft retail building with a drive-through.
The roads and utilities around the site were changing. Lake Sharon Drive was being expanded and public utilities were changing. The I-35 expansion and right-of-way dedications also had to be worked out with TxDOT.
The site also had to manage its own drainage plus drainage arriving from off site.
MES managed the plan development and the approval process. The design kept to zoning rules, building codes and the other guidelines that applied.
The team worked with the City of Corinth through the Lake Sharon Drive expansion and the utility changes.
It worked with TxDOT on the I-35 expansion and the right-of-way dedications, so the project met the regulations and requirements that applied.
The frontage driveway on the I-35 access road went through an approval process with TxDOT and the City of Corinth. MES worked through the challenges along the way and won that approval.
MES designed a detention pond that manages both the new development's runoff and the existing off-site drainage.
The driveway was approved and the center was built.
Photos from September 2022 show the stone and brick buildings finished, with new paved parking, landscaped beds and young trees in place.
More projects

1.0 MGD zero-discharge reuse for a mixed-use development

2.0 MGD wastewater reuse authorization for a mixed-use development

Industrial zero-discharge reuse in Taylor, TX, approved within 6 weeks of submission
Talk to an engineer
Not a salesperson. Someone who can tell you whether the pathway is real.
Your options, the agencies involved and the questions that decide cost and schedule.