How is it that we are going to be able to confirm if there are no city requirements?

With no city requirements, BESS permitting in Texas still runs through the county, the state and the fire service. Here is how to confirm each one in writing.

You confirm it with the other agencies that still have a say on your battery energy storage system (BESS). No city requirements usually means the city has no authority over your tract, not that the tract is unregulated. BESS permitting in Texas can run through the county, the state and the fire service, each answering on its own terms.

Project photo: an aerial view of a water storage tank during construction

What does it mean when there are no city requirements?

It means the city is not the permitting authority for that tract, and nothing more. It is not a finding that the site is unregulated, and it does not cover the county, the state or the fire service.

The statement usually answers a narrower question than the one you asked. Someone asked the city about zoning, or about a utility connection, and got a clean no. That answer is true for the question. It says nothing about whether the county permits grading on the same land.

An address is not a jurisdiction. Start with the parcel and the county it sits in, then ask whether the tract is inside a city limit. The city that matters is the one with authority over the land, not the one on the mailing address.

Who still has authority when the city does not?

Usually the county, the state and the fire service that would respond to the site. Each has its own trigger, so each needs its own answer in writing.

The county's trigger is often ground disturbance. Collin County's development services page (opens in a new tab) says anyone planning residential or commercial work that disturbs ground or adds footprint in the unincorporated county must apply for a permit through the county's Citizen Self-Service Portal. One county's page is not another county's rule, so you ask the county your tract sits in.

The state's trigger can be the facility itself. Texas Utilities Code Chapter 187 (opens in a new tab) requires the operator to provide a site-specific emergency operations plan to the local first responder responsible for fire protection in the area before the commercial operations date, and to keep safety data sheets on site.

The state's other trigger is the driveway. Gillespie County's brochure on TxDOT access permits (opens in a new tab) says a permit is required so the driveway location meets TxDOT's criteria and regulations for access to the state highway system, and that there is no fee for it. A county road frontage raises a county access question instead.

MES has done civil site work for a battery storage developer in Guadalupe County, Texas. Outside a city limit, the county and state questions are still on the list.

How do you confirm a county's requirements in writing?

Ask one specific question about your parcel and get the reply in writing. An email or a portal submittal is worth more than a phone call, because it is an answer your investor and your EPC can both rely on.

Give the county three things:

  • The parcel address or account number
  • The work you plan, named plainly: grading, a driveway, drainage, equipment pads, a fence
  • The phase you are in

Each one raises a different question, so name the work in the message rather than calling it site work.

Then ask for the negative in writing. If no county permit applies, ask the reviewer to say so in an email. A written no is a document you can hand to your EPC and your lender, and it costs one message.

What should the confirmation cover before you commit to the site?

It should cover every agency with a trigger on the tract, not just the one that answers first. A clean city answer plus an open county question is not a cleared site.

Run the list below against what you hold in writing. A site is ready to price only when every item is a yes.

  1. You know whether the tract is inside a city limit, from the city or county with authority over it, in writing.
  2. You have the county's written answer on ground disturbance for your parcel, including grading and the driveway.
  3. You know which fire service would respond, and you have asked what it will review and what it needs to see.
  4. You know whether the driveway meets a state-maintained highway, and whether TxDOT has issued an access permit on it.
  5. You have filed every written answer with the EPC's site plan, so the layout does not move after the equipment order.

Pass rule: ready only when every item is a yes. A single no is an open cost and an open date, and it belongs on the risk list you take to your investment committee.

Before you spend design money, a screen of the tract answers these questions in a fixed scope, with the open risks listed. Take three questions to your engineer:

  • Which agency holds the longest clock
  • What each submittal has to contain
  • What changes if one answer comes back different

Confirmation work only pays off if it runs ahead of the equipment order. A late permit answer moves the layout, and the layout moves the schedule.

What if the county says it has no rules for battery storage?

Treat that as a starting point, not a clearance. A county with no battery storage ordinance can still require a permit for ground disturbance, as Collin County's ground-disturbance requirement shows, and the state duties apply either way.

Ask two follow-ups. Does the work need a development, grading or driveway permit, and who signs off on access? Then ask the fire service what it will review and what it needs to see before it will sign.

Re-ask before you file. The reviewer, the ordinance and the fire service contact can all change between your first call and the submittal.

This article is general education on how to confirm which agencies have authority over a battery storage site in Texas. It is not a site-specific determination, it does not promise any agency's answer or a review timeline, and one agency's written answer does not speak for another.

Frequently asked questions

Does no city requirement mean no permit is needed?

No. It means the city is not the authority over the tract. The county, the state or the fire service can still require a permit or a submittal.

Black-and-white street map graphic of a large city and its surrounding suburbs, showing roads, highways and a lake.
Black-and-white street map graphic of a large city and its surrounding suburbs, showing roads, highways and a lake.

How do I find out if my site is inside a city limit?

Ask the city and the county that cover the parcel, and ask for the answer in writing. Use the parcel, not the mailing address.

What if the county says it has no battery storage rules?

Ask what the work itself triggers, such as a grading, development or driveway permit, and confirm the answer in writing.

Who do I ask about fire requirements outside city limits?

The local first responder responsible for fire protection in your area, which is where Chapter 187 sends the emergency operations plan.

How early should I confirm county requirements?

Before the EPC fixes the fenced layout and before the equipment order. A late answer moves the layout, and the layout moves the schedule.

Not sure what applies when the city says it has no requirements?

MES is a civil engineering design firm working in water, wastewater and site civil engineering for land development. On a battery storage tract we find which agencies have a trigger, ask each one in writing, and put the driveway, drainage, plat and fire service answers in the order that holds your date.

Ask for the first step: sealed site assessment per site. What the permits will take (access, drainage, plat, fire code and water supply), the order to start them, and a low-to-high cost range (Draft report within 3 business days after the site walk). Ask for it here.

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.