Business park reuse after a county septic denial in Taylor, TX
A TCEQ 210E reuse authorization in 4 weeks kept a Taylor, Texas, business park on schedule after the county denied septic.
Read the projectWastewater engineering
If your project has an eligible industrial wastewater stream and somewhere to reuse the water every day, a TCEQ 210E authorization can stand in for a discharge permit for that water.
It is TCEQ's written approval to reuse industrial wastewater, alone or mixed with domestic sewage, for irrigation and other approved uses instead of discharging it. The rules are in 30 TAC Chapter 210, Subchapter E. Level II reuse needs TCEQ's approval on Form TCEQ-20094 before it starts, and the application has no public notice step.
An all-domestic project cannot use 210E. Industrial wastewater with any domestic sewage in it is commingled, and the plant must meet the stricter reclaimed water quality standards. A rule effective March 2025 (§210.2(e)) reads as asking for a treatment permit too. In our experience, TCEQ has not required one for a commingled 210E plant, but site facts can change that, so we confirm it for your project.
These show what an eligible, complete application can do. They are not a promise for yours.
Completeness matters most: the reuse land, storage and backup settled before filing, not during review. Larger flows draw more detailed review. Engineering cost follows the design flow, the wastewater mix, effluent testing and the reuse site. After approval, the owner samples the water and keeps records for five years.
An engineer reads your note and tells you the pathway, the agencies involved and what decides cost and schedule.
Talk to an engineerProjects

Taylor, TX
A TCEQ 210E reuse authorization in 4 weeks kept a Taylor, Texas, business park on schedule after the county denied septic.
Read the project
Taylor, TX
A TCEQ 210E reuse authorization, approved within 6 weeks of submission, let an industrial site in Taylor, Texas, start operations on schedule after the county denied septic.
Read the project
Martindale, TX
A 2.0 MGD 210E reuse authorization in 4 weeks, about 23 months faster than a discharge permit.
Read the projectKeep reading
Talk to an engineer
Not a salesperson. Someone who can tell you whether the pathway is real.
Your options, the agencies involved and the questions that decide cost and schedule.
No commitment to have the first call.
Prefer the phone? (214) 833-6748