Wastewater engineering

210E reclaimed water authorizations in Texas

For sites with an eligible industrial stream: our four 210E authorizations took 4 to 10 weeks, where nearby discharge permits took 30+ months.

What this covers

  • 210E reclaimed water authorization
  • Reclaimed water storage pond, irrigation pump station and distribution

What a 210E authorization is

It is TCEQ's written approval to reuse industrial wastewater, alone or mixed with domestic sewage, for irrigation and other approved uses instead of discharging it. The rules are in 30 TAC Chapter 210, Subchapter E. Level II reuse needs TCEQ's approval on Form TCEQ-20094 before it starts.

A 210E authorization needs an industrial wastewater stream. An all-domestic project cannot use it, and a mixed-use project qualifies only through its industrial stream. Industrial wastewater with any domestic sewage in it is commingled, and the plant must meet the stricter reclaimed water quality standards. Where domestic sewage is mixed in, 30 TAC §210.2(e) may also require a discharge permit or a land application permit, so we confirm the path with TCEQ before design. The 210E application itself has no public notice step; any companion permit has its own.

When it fits

  • The site has an industrial stream that §210.54 does not exclude. Hazardous wastewater, most categorical process wastewater and grease trap waste are out.
  • The county denied a septic permit, or a discharge permit would draw opposition.
  • You control the reuse land or hold a signed agreement with the user.

What we do

  1. Check eligibility: the stream, the exclusions, and whether it is commingled.
  2. Build the reuse plan: end uses, irrigation area and a water balance, with storage sized for the days you cannot irrigate.
  3. Name the backup. The application must say where water goes when reuse stops. A backup discharge needs its own permit.
  4. Prepare the application and answer TCEQ's questions.
  5. Design the system: the storage pond, irrigation pump station and distribution.

What you get

  • A written eligibility answer before you commit to the path.
  • The application with its water balance, storage sizing and reuse documentation.
  • Sealed design for the reuse system.

Results on four Texas projects

  • A business park in Williamson County, after the county denied septic: authorized in 4 weeks.
  • An industrial site in Williamson County: within 6 weeks of submission.
  • A 2.0 MGD wastewater plant in Caldwell County: 4 weeks.
  • A 1.0 MGD project in Hays County with industrial cooling, cleaning and washout flows: 10 weeks.

These show what an eligible, complete application can do. They are not a promise for yours.

What affects time and cost

Completeness matters most: the reuse land, storage and backup settled before filing, not during review. Engineering cost follows the design flow, the wastewater mix, effluent testing and the reuse site. After approval, the owner samples the water and keeps records for five years.

For developers weighing the path before closing, see 210E reclaimed water authorizations for Texas developments.

More on wastewater engineering

Start with a first answer

An engineer reads your note and tells you the pathway, the agencies involved and what decides cost and schedule.

Talk to an engineer

Projects

Work like this

Packaged wastewater treatment unit with a screen and railed platform on a concrete pad, with piping and tanks nearby.

Williamson County, TX

Business park reuse after a county septic denial in Williamson County, TX

A TCEQ 210E reuse authorization in 4 weeks kept a Williamson County, Texas, business park on schedule after the county denied septic.

Read the project
Packaged wastewater treatment plant seen from above, with cream-colored tanks, concrete pads and a skid steer.

Williamson County, TX

Industrial zero-discharge reuse in Williamson County, TX, approved within 6 weeks of submission

A TCEQ 210E reuse authorization, approved within 6 weeks of submission, let an industrial site in Williamson County, Texas, start operations on schedule after the county denied septic.

Read the project
Packaged wastewater treatment plant on a concrete pad with white process piping, stainless steel tanks and site lighting under an overcast sky

Caldwell County, TX

2.0 MGD reuse authorization for a development with a data center and batch plant

A 2.0 MGD 210E reuse authorization in 4 weeks, where nearby discharge permits took 30+ months.

Read the project

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.