2.0 MGD wastewater reuse authorization for a mixed-use development

A 2.0 MGD 210E reuse authorization in 4 weeks, about 23 months faster than a discharge permit.

Packaged wastewater treatment plant on a concrete pad

About the project

The problem

A master-planned development near Martindale, Texas needed wastewater service for homes, data center operations and a concrete batch plant. The design flow is 2.0 MGD.

Discharge permits in Caldwell County near the San Marcos River watershed face close scrutiny from regional water authorities and environmental groups.

At public hearings for neighboring discharge permit applications, MES staff saw contested timelines of more than 30 months.

The pathway

MES took the project down the 210E reuse pathway, which rests on showing a beneficial agricultural reuse of the treated water.

The reuse plan sends treated water to off-site agricultural irrigation at a local tree farm and sod operation, under a reuse agreement with that operation.

It also includes a 53 acre-foot storage reservoir, designed to 30 TAC 309.20 with 25-year worst-case precipitation data.

The result

The project received a TCEQ 210E authorization in 4 weeks, about 23 months faster than a discharge permit.

At 2.0 MGD, it is one of the largest 210E authorizations MES has secured. It shows that flow volume does not rule out 210E when industrial flows and a workable reuse plan are present.

The reuse agreement gives the development long-term disposal certainty and supports local agriculture.

As the development grew, the owner later began a TCEQ discharge permit application for the wastewater plant in 2026.

Authorization
TCEQ 210E
Time to permit
4 weeks
Time saved vs discharge permit
About 23 months
Design flow
2.0 MGD
Reuse storage
53 acre-foot reservoir
Reuse
Off-site agricultural irrigation
  • 210E reuse authorization
  • Wastewater permitting
  • Water balance and storage sizing

Talk to an engineer

Tell us about your project.

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Read our privacy policy.