MES quantified water loss and I&I for the town and delivered a final report with engineering estimates and a prioritized roadmap in 2024; follow-up work continues in 2026.
Town of Oak Creek I&I and water loss analysis

Project
Four miles of waterline moved clear of TxDOT IH-20 work while Bitter Creek customers kept water service.
Waterline relocation trench near Sweetwater, Texas, October 2024
TxDOT improvements along the IH-20 corridor in Sweetwater, Texas required four miles of existing Bitter Creek Water Supply Corporation waterline to be relocated to avoid conflict with the road project.
Bitter Creek customers needed their water service to stay on throughout the work.
MES worked directly with TxDOT officials so the relocation met the agency's specifications, requirements and timelines.
During construction, MES provided on-site engineering. Staff made regular site visits, flew drone inspections along the waterline and reviewed shop drawings against the design.
In the field, MES set out next steps with the contractors, surveyors and Bitter Creek staff. The team worked through grading and existing utility questions as they came up.
MES wrote field reports during construction and prepared the payment requests submitted to TxDOT for reimbursement.
The four miles of waterline were moved clear of the TxDOT project, and Bitter Creek customers kept water service throughout the work.
Field work wrapped up in December 2024. The last field report, number 60, is dated December 22.
In February 2025, MES sent TxDOT the final pay application and the as-built drawings.
More projects

Town of Oak Creek I&I and water loss analysis

Mountain Water and Sanitation District plant upgrades and line rehabilitation

Phippsburg and Milner wastewater plants and collection system
Talk to an engineer
Not a salesperson. Someone who can tell you whether the pathway is real.
Your options, the agencies involved and the questions that decide cost and schedule.
No commitment to have the first call.
Prefer the phone? (214) 833-6748