Packaged wastewater treatment unit with a screen and railed platform on a concrete pad, with piping and tanks nearby.

Project

Business park reuse after a county septic denial in Taylor, TX

A TCEQ 210E reuse authorization in 4 weeks kept a Taylor, Texas, business park on schedule after the county denied septic.

Photo from another MES project

The problem

A business park in Taylor, Williamson County, Texas, needed a wastewater solution.

Williamson County denied the septic permit: the park's platting issues and site constraints ruled out conventional on-site treatment.

A discharge permit would have added a long review and possible opposition on top of the plat and fire marshal reviews the park already needed.

The pathway

MES pursued a TCEQ 210E reuse authorization instead. That moved the wastewater review from the county to TCEQ, with a zero-discharge reclaimed water system.

The system takes domestic wastewater, cooling system water, and water from equipment cleaning and facility maintenance. The cooling and cleaning water is the industrial stream the 210E rests on.

The reclaimed water irrigates the business park's landscaping and supplies its fire protection system.

MES also did the site civil design: site, utility, paving and grading plans, plus drainage calculations and a drainage report.

The team drew the wastewater management plan, with its sewer and irrigation lines, sprayer head fields and wastewater pond grading.

MES prepared the fire line plans and the submittals for Williamson County fire marshal review.

MES also prepared the plat application and submitted it to Williamson County.

The result

TCEQ approved the 210E authorization in 4 weeks, while MES carried the plat, the site civil plans and the fire marshal submittals through Williamson County.

The 4-week approval let the developer keep its construction schedule.

The 6,700 gallon per day system has no off-site discharge.

Design flow
6,700 gallons per day
Authorization
TCEQ 210E
Time to permit
4 weeks
Discharge permit path
TCEQ asks applicants to file at least 330 days before discharge begins
Reuse
Landscape irrigation and fire protection
  • 210E reuse authorization
  • Site civil design
  • TCEQ permitting
  • Platting

More projects

Other work like this

See all projects

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.