Find the right TCEQ permit path before you file
Compare TCEQ discharge permits, TLAPs and 210E reuse authorizations for your Texas site, with permitting, drawings and WWTP design from one engineering firm.
Talk to an engineer or call (214) 833-6748
For a new domestic discharge permit, TCEQ asks applicants to file at least 330 days before discharge begins (opens in a new tab). A project with an industrial wastewater stream may qualify for a 210E reuse authorization instead, and the 210E application itself has no public notice step. We find the path your site qualifies for before you commit money to one.
- A 210E reuse authorization, where your project qualifies
- Carrying costs weighed in the permit path decision
- A schedule built on TCEQ's published steps, not guesses
How we work
Fixed fees, not padded timesheets
We price most work as a fixed fee for a defined deliverable. Where the scope cannot be fixed, such as agency comments or overflow support, we quote time and materials with a budget. You know the cost before work starts.
Schedule as a design input
Time to permit and time to construction sit beside hydraulics and code in our process. Delays cost more than drawings, so we design with schedule as a core constraint. We commit our production times in writing. Agency review times are the agency's.
We talk in cost, timeline and risk
Your pro forma matters to us because engineering decisions are business decisions. No translation needed.
Less admin, more engineering
We use AI to cut admin work, so our engineers spend their time on your project. A licensed PE makes every technical call. From your first call to construction closeout, you work with one team.
What we handle for you
We take Texas developers from land acquisition to groundbreaking, with permitting and construction drawings running in parallel.
Wastewater treatment planning
Not sure if you need a package plant, a concrete WWTP or a reuse system? We evaluate your site, flows and budget, and you get clear options with cost comparisons before you commit to a path.
TCEQ permitting
A new domestic discharge permit carries public notice, a comment period and the chance of a contested case hearing. TCEQ's own training slides on industrial reuse authorizations (opens in a new tab) estimate about 60 to 90 days from submittal for a 210E. That is TCEQ's estimate, not a promise. On our projects, the fastest 210E authorizations took 4 weeks, where nearby discharge permits took 30+ months.
A 210E authorization needs an industrial wastewater stream. An all-domestic project cannot use it, and a mixed-use project qualifies only through its industrial stream. Where domestic sewage is mixed in, 30 TAC §210.2(e) (opens in a new tab) may also require a discharge permit or a land application permit, so confirm the path with TCEQ before design. The 210E application itself has no public notice step; any companion permit has its own.
A Texas Land Application Permit (TLAP) for irrigation is another option, but it follows the same notice steps as a discharge permit. We check which paths fit your site before you file.
Construction drawings
Permitting and construction drawings run in parallel. We deliver permit-ready civil plans, utility layouts and technical details built to the reviewer's checklist, so first-round comments are short.
Infiltration and inflow analysis
Excess stormwater entering your sewer system causes capacity problems and permit issues. We find where infiltration and inflow are occurring and design fixes that reduce flows and keep your system in line with TCEQ requirements.
Hydraulic modeling
We model your collection and distribution systems to find capacity limits, pressure problems and future expansion needs, so they show up in design, not during construction or after tenants move in.
Collection system design
From gravity sewers to force mains, we design collection systems sized for your development's actual flows, whether you connect to a city system or feed a private WWTP.
Lift station design
When gravity will not work, you need a lift station that is reliable, cost-effective and easy to maintain. We size the pumps, controls and redundancy for your flows.
Construction administration
We stay engaged through construction with submittal reviews, RFI responses and site visits. When issues come up, you have an engineer who knows your project.
Need something else? See all our services.
About MES
Founded in 2018, MES has completed 525+ projects across Texas, Colorado and beyond. We work on water, wastewater and site civil for land development, and we run TCEQ strategy, site plans, construction drawings and WWTP design as one team from concept to closeout.
Why developers choose MES
- TCEQ permitting. We bring working knowledge of TCEQ's process and alternative pathways. Where a project qualifies, we use a 210E reuse authorization. Where it does not, we plan the discharge permit or TLAP around TCEQ's filing guidance.
- Everything under one roof. Permitting, site plans, construction drawings and WWTP design, coordinated by one team.
- PE-reviewed deliverables. A licensed PE reviews every plan set and report before delivery.
- Responsive communication. We answer in days, not weeks, and you work with the engineer doing the work.
- Predictable costs. A fixed fee for a defined deliverable on most work, with the scope written down before we start.
- Track record. 525+ completed projects, including commercial warehouses, industrial parks and package WWTPs.
Projects
Mixed-use development in San Marcos, Texas
A new 1.0 MGD discharge permit in the San Marcos area was likely to draw opposition over the San Marcos River and the Edwards Aquifer recharge zone, and a discharge permit carries public notice, a comment period and the chance of a contested case hearing. The project qualified for a 210E through its industrial streams and uses a zero-discharge reuse system, which avoided a new surface water discharge. It was authorized in 10 weeks.
Location: San Marcos, Hays County, Texas
Authorization: TCEQ 210E
Project type: Large-scale mixed-use development combining industrial uses, commercial facilities and supporting infrastructure
- Design flow: 1.0 MGD
- Industrial streams: cooling systems, equipment cleaning, humidification processes and truck washout, with domestic wastewater
- Reuse: on-site irrigation of campus landscaping and common areas, and fire protection for on-site buildings
Mixed-use development near Martindale, Texas
Discharge permits in Caldwell County near the San Marcos River watershed draw close scrutiny from regional water authorities and environmental groups. MES staff attended public hearings on neighboring discharge permit applications and saw how contested they were. The project qualified for a 210E through its industrial streams, with an agricultural reuse plan at a local tree farm and sod operation that gives long-term disposal certainty. It was authorized in 4 weeks.
Location: Martindale, Caldwell County, Texas
Authorization: TCEQ 210E
Project type: Master-planned mixed-use development combining residential subdivisions, data center operations and a concrete batch plant
- Design flow: 2.0 MGD
- Industrial streams: data center wastewater, 120,000 gpd (6.0%), and concrete batch plant wastewater, 600 gpd (0.03%). Municipal wastewater makes up most of the design flow.
- Reuse: off-site agricultural irrigation at a local tree farm and sod operation, with a 53 acre-foot storage reservoir
Business park in Taylor, Texas
Williamson County denied the septic permit because platting issues and site constraints made conventional on-site treatment infeasible. The 210E authorization, through the park's industrial streams, moved the project to TCEQ oversight with a zero-discharge reclaimed water system, and the developer kept its construction schedule. It was authorized in 4 weeks.
Location: Taylor, Williamson County, Texas
Authorization: TCEQ 210E
Project type: Mixed-use business park combining industrial operations with commercial and office facilities
- Design flow: 6,700 gpd
- Industrial streams: cooling systems, equipment cleaning and facility maintenance, with domestic wastewater
- Reuse: on-site landscape irrigation and a fire protection system
Industrial site in Taylor, Texas
Williamson County denied the septic permit over industrial wastewater constituents and site geology, so on-site disposal was not viable. The 210E path gave the facility an industrial reclaimed water system with self-contained on-site reuse and no off-site discharge, and it started operations on schedule.
Location: Taylor, Williamson County, Texas
Authorization: TCEQ 210E
Project type: Industrial facility with process wastewater, industrial washwater and domestic wastewater
- Design flow: 5,000 gpd
- Reuse: on-site landscape irrigation and a fire protection system
Questions developers ask
How long does a TCEQ permit take?
For a new domestic discharge permit, TCEQ asks applicants to file at least 330 days before discharge begins, and public notice, comments and any contested case hearing fall inside that window. A 210E reuse authorization has no public notice step, and TCEQ's training slides estimate about 60 to 90 days from submittal. Those are TCEQ's figures, not guarantees, and a notice of deficiency adds time. We help you pick the path before you commit.
What is the difference between discharge, land application and reuse?
Where your treated water goes decides which paths you can use. A TPDES discharge permit lets you release treated wastewater into a creek or river, with public notice, a comment period and the chance of a contested case hearing. A Texas Land Application Permit (TLAP) covers disposal by irrigation or other land application, and follows the same notice steps. A 210E authorization covers reuse of an industrial wastewater stream: an all-domestic project cannot use it, and a mixed-use project qualifies only through its industrial stream. Where domestic sewage is mixed in, 30 TAC §210.2(e) may also require a discharge permit or a land application permit, so confirm the path with TCEQ before design.
Can you help if we are already stuck in the TCEQ queue?
Yes. We have helped developers change permitting strategy mid-project. If your current approach is stalled, we can evaluate alternatives such as a 210E reuse authorization, if your project qualifies, or a permit modification.
What happens if TCEQ rejects our submittal?
A rejection resets the review clock. The redesigned resubmittal goes back through TCEQ review while your carrying costs keep running. That is why we confirm the right permit path, and check the design against it, before the first submittal.
Which Texas counties do you work in?
We work across Texas, with experience in DFW (Collin, Dallas, Denton, Ellis and Tarrant counties), the Austin area (Hays, Bastrop, Williamson and Travis), the Houston area (Fort Bend, Montgomery and Harris) and San Antonio (Bexar, Comal and Guadalupe). If you are building in the ETJ or an unincorporated area, we likely know the local rules.
Can you help during due diligence before we close on land?
Yes. A feasibility review during your due diligence window tells you the utility costs, permitting pathways and risks before you close, and can keep you out of a permit path that does not fit your site.
Do you only do permitting, or design too?
Both. From concept drawings to construction-ready plan sets, we run permitting and design in parallel: site plans, utility layouts, construction drawings and WWTP design, under one roof.
What types of projects do you work on?
Commercial warehouses, industrial parks, mixed-use developments, data centers, manufacturing facilities, food distribution, cold storage and logistics centers. Most are in the ETJ or unincorporated areas where city utilities are not available.
Do you design wastewater treatment plants?
Yes. From package plants to custom concrete systems, we design treatment systems sized for your flows and budget, from about 5,000 gpd to 2 MGD. We handle equipment vendor coordination, reuse system design and the design work your plant needs for permitting and construction.
What if my site civil engineer is already handling utilities?
We often work alongside site civil engineers. They handle grading, paving and drainage; we handle the water and wastewater scope. We can join your existing team or lead the utilities, whichever suits your project.
How fast can you start on a new project?
We confirm a start date with you before you sign. For an urgent feasibility review during due diligence, tell us your deadline up front.
How do you charge?
We price most work as a fixed fee for a defined deliverable. Where the scope cannot be fixed, such as agency comments or overflow support, we quote time and materials with a budget.
Who will we be working with?
Licensed engineers who stay on your project from kickoff to closeout. You have a direct line to the people doing the work.
Are you licensed in Texas?
Yes. MES is licensed in nine states: Texas, Colorado, California, Oklahoma, Nevada, Arizona, Florida, Kansas and New Mexico. On Texas projects, deliverables are reviewed by, and where required sealed by, a Texas PE.
How long have you been in business?
MES was founded in 2018 by Michael Groselle, PE. We have completed 525+ projects across Texas and beyond, in water, wastewater and site civil engineering for land development.
What makes you different from larger firms?
We answer in days, not weeks, and you work with the engineer doing the work. We talk in cost, timeline and risk, and we focus on water, wastewater and site civil.
Do you only work with developers?
No. We also work with municipalities, water districts and engineering firms that need overflow support or water and wastewater depth. Our Texas developer practice is built for commercial and industrial projects in the ETJ and unincorporated areas.
Where are you located?
Our headquarters is in McKinney, Texas, with offices in Golden, Colorado, and San Jose, California. Our team works across several states, and our Texas engineers know TCEQ and county requirements.
What clients say
"Mike and his team were successful in securing the permit much quicker than we anticipated."
John Petersen
"This site had challenging topography and their design team was able to integrate various design features to make the site I wanted work."
Massud Mojra
"Michael's Team is reliable and professional."
Brett Hornung
Talk to an engineer
Tell us about your site and we will tell you which permit path fits. An engineer reads every message and gives you a first answer.
Talk to an engineer or call (214) 833-6748
Talk to an engineer
Tell us about your project
An engineer reads it
Not a salesperson. Someone who can tell you whether the pathway is real.
You get a first answer
Your options, the agencies involved and the questions that decide cost and schedule.
You decide
No commitment to have the first call.
Prefer the phone? (214) 833-6748