A 2.0 MGD 210E reuse authorization in 4 weeks, nearly a year faster than a discharge permit.
2.0 MGD wastewater reuse authorization for a mixed-use development

Project
A TCEQ 210E authorization in 10 weeks let a 1.0 MGD mixed-use development in San Marcos bypass a discharge permit and its hearings.
A similar system on another MES project
A large mixed-use development in San Marcos, Hays County, Texas, combines industrial uses with commercial facilities and supporting systems. Its wastewater facility has a design flow of 1.0 MGD.
A discharge permit at that size would have faced significant opposition from environmental groups concerned about the San Marcos River and the Edwards Aquifer recharge zone. In this region, public hearing processes routinely stretch those timelines to 30 months or more.
MES pursued the TCEQ 210E authorization instead, with a zero-discharge reclaimed water system. All of the reuse stays on site, so there is no surface water discharge.
The waste streams include domestic wastewater, cooling systems, equipment cleaning, humidification, truck washout and stormwater runoff.
The reclaimed water has two uses. It irrigates the campus landscaping and common areas, and it supplies fire protection for the industrial and commercial buildings.
MES studied the site and the TCEQ requirements, brought the topography into the design files, and prepared the plans, report and exhibit. The application went out in July 2025.
TCEQ approved the 210E authorization in 10 weeks, even with the more detailed review a 1.0 MGD system needs. For a new discharge permit, TCEQ’s own guidance is to file at least 330 days before discharge begins.
The project’s industrial component provided clear justification. The large irrigation capacity removed any surface water discharge concern.
More projects

2.0 MGD wastewater reuse authorization for a mixed-use development

Industrial zero-discharge reuse in Taylor, TX, approved within 6 weeks of submission

Business park reuse after a county septic denial in Taylor, TX
Talk to an engineer
Not a salesperson. Someone who can tell you whether the pathway is real.
Your options, the agencies involved and the questions that decide cost and schedule.
No commitment to have the first call.
Prefer the phone? (214) 833-6748