Plans and permit work on 43 site addresses for an ice vending company in Arizona and Florida
Ice vending site permits across Arizona and Florida

Project
MES has sent out site and utility plan sets for three Florida ice vending machine sites since July 2025, each within two weeks, and is designing a water service for a fourth.
Ice vending site, Freeport, Florida
An ice vending machine operator needed civil plans for four of its machine sites in Florida, including Freeport, Fort Myers and Jacksonville.
Three of the sites needed a site and utility plan set.
The Jacksonville machine sits in the parking lot of a host property and runs on a shallow well. The operator wants a potable water service from the local utility so the well can be disabled.
For each of the first three sites, MES drew a plan set with a cover sheet, a survey sheet, a site plan and a utility plan.
The Freeport set also carried a demolition sheet. MES later wrote a drainage letter for that site.
The third set showed two utility options.
Each set was reviewed and revised before it went out.
For Jacksonville, the scope is a water service plan signed and sealed by a Florida-licensed Professional Engineer. It shows the point of connection to the utility's water main, the meter and backflow prevention assembly, and the service line from the meter to the machine along the drive aisle. It also notes that the existing well supply is to be disconnected at the machine.
MES will submit the plan to the utility and answer its review questions.
Three plan sets have gone out. Each went out within two weeks of the start of work on it: Freeport in July 2025, Fort Myers in November 2025 and the third site in July 2026.
The Jacksonville water service plan is in design now.
The operator has brought MES four sites since July 2025.
More projects
Ice vending site permits across Arizona and Florida

Drive-up water kiosk site program in seven states

Business park reuse after a county septic denial in Taylor, TX
Talk to an engineer
Not a salesperson. Someone who can tell you whether the pathway is real.
Your options, the agencies involved and the questions that decide cost and schedule.
No commitment to have the first call.
Prefer the phone? (214) 833-6748