Packaged wastewater treatment plant seen from above, with cream-colored tanks, concrete pads and a skid steer.

Project

Industrial zero-discharge reuse in Taylor, TX, approved within 6 weeks of submission

A TCEQ 210E reuse authorization, approved within 6 weeks of submission, let an industrial site in Taylor, Texas, start operations on schedule after the county denied septic.

A similar system on another MES project

About the project

The problem

An industrial-only facility in Taylor, Williamson County, Texas, produces process wastewater and wastewater from equipment cleaning.

Williamson County denied the septic permit. Its concerns were the industrial wastewater constituents and the site's geological limits.

Traditional on-site disposal was not viable. A discharge permit would have faced a long review and possible opposition.

The pathway

MES pursued a TCEQ 210E reuse authorization instead. The system treats domestic wastewater, process wastewater and industrial washwater, then reuses the reclaimed water on site.

It is sized for a design flow of 5,000 gallons per day.

The 210E pathway gave the site clean industrial reclaimed water under TCEQ oversight.

The reclaimed water goes to landscape irrigation and to the fire protection system. The system is self-contained, so no wastewater is discharged off site.

MES ran the calculations, prepared and updated the application, drafted a letter and finished a specification.

The result

TCEQ granted the 210E authorization within 6 weeks of submission. That is nearly a year sooner than a discharge permit would have taken, and more if it had been contested.

The authorization let the facility start operations on schedule. Its reuse system removes any off-site discharge concern and gives the facility complete control of its operation.

Design flow
5,000 gallons per day
Authorization
TCEQ 210E
TCEQ approval
Within 6 weeks of submission
Time saved vs. discharge permit
Nearly a year, more if contested
Reuse
Landscape irrigation and fire protection
  • 210E reuse authorization
  • Industrial wastewater
  • TCEQ permitting

More projects

Other work like this

See all projects

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.