Industrial zero-discharge reuse in Taylor, TX, approved within 6 weeks of submission

A TCEQ 210E reuse authorization, approved within 6 weeks of submission, let an industrial site in Taylor, Texas, start operations on schedule after the county denied septic.

Photo from another MES project

The problem

An industrial-only facility in Taylor, Williamson County, Texas, produces process wastewater and wastewater from equipment cleaning.

Williamson County denied the septic permit because of what the industrial wastewater contained and the site's geological limits.

With process wastewater in the mix, on-site disposal was ruled out, and a new discharge permit would have meant a long review before the facility could open.

The pathway

MES pursued a TCEQ 210E reuse authorization instead. The system treats domestic wastewater, process wastewater and industrial washwater, then reuses the reclaimed water on site.

It is sized for a design flow of 5,000 gallons per day.

Under 210E, the site reuses its treated water under TCEQ oversight.

The reclaimed water goes to landscape irrigation and to the fire protection system. The system is self-contained, so no wastewater is discharged off site.

MES ran the calculations, prepared and updated the application, drafted a letter and finished a specification.

The result

TCEQ granted the 210E authorization for the 5,000 gallon per day industrial system within 6 weeks of submission.

The authorization let the facility start operations on schedule, treating its own process water and washwater on site.

Design flow
5,000 gallons per day
Authorization
TCEQ 210E
TCEQ approval
Within 6 weeks of submission
Discharge permit path
TCEQ asks applicants to file at least 330 days before discharge begins
Reuse
Landscape irrigation and fire protection
  • 210E reuse authorization
  • Industrial wastewater
  • TCEQ permitting

More projects

Other work like this

See all projects

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.