Closing on Texas data center land before you have water and wastewater in writing
You need three written answers before money goes hard: how much water you need per day by phase, where that supply actually comes from and who documents it, and where the wastewater goes and who authorizes it. Supply and wastewater usually get pushed to later, and that order is what costs developers months. On the show we walked through what to ask for and how to check the utility behind the answer.

Why does the land deal move faster than the water answer?
The land gets committed first, and the water and wastewater answers get written into the data room as something to worry about later. That order is the risk.
Cities are starting to look at water before they look at the building. San Antonio's council set new data center regulations on October 30, and we expect more cities to follow with their own rules.
A nearby main, the right zoning or a utility saying "we'll work with you" is not service. Demand is what you ask for.
One Texas developer told us they were several months behind because of the third party reviewer that was requested. Of the 37 Texas developers we have spoken with since April 2026, 29 described something similar.
What proof should you have in hand before you close?
Three separate written answers, not three steps you run in order. A site fails if any one is missing.
Demand: gallons per day by phase. How much you need depends largely on how you cool the facility. Texas planning numbers run about 250 gallons per day per single family home, so you convert your daily demand to LUEs to talk to a utility in its own units.
Source of supply: trace the water back to its source and name who documented it. Not just which utility will serve you, but where that utility actually gets the water.
Wastewater destination: where it goes and who authorizes it. Options include septic, an on-site 210 authorization, or a lift station pumping to the city main.
Each line gets either a document or a blank. The blanks are what you negotiate before you close, not after.
What does a capacity letter leave out?
Often the capacity itself. On one project a small utility's wells did badly in droughts, and the wholesale contract behind the numbers did not cover our full buildout.
That small Texas water system could sell about 100 LUEs at most. The data center nearby was asking for several hundred.
The land was fine. The utility could not carry it. The fix sat on a 10-year regional plan, with water right and legal fees and upgraded storage tanks and pumps, and costs in the $20 million range are not a shock at that scale.
What to ask for in writing: capacity by phase, the wholesale contract it relies on, and any storage or pump project that is actually on a docket.
Water Provider Feasibility work starts with the water proof a Texas city site should have first.
How do you check whether the utility is reliable?
Read its water loss. The benchmark we use is 10%, and one small Texas water utility has lost 45% of its water for five to six years, roughly four times over.
Some utility directors do not know their own numbers. Ask straight during due diligence and see what comes back.
Low loss does not create capacity. It only says the water the utility does have is better managed.
The same rule applies where the destination is a city plant or lift station. Ask for documented capacity, not a pending permit.
If the utility cannot serve you, can your own well carry the load?
Do not assume a well rescues the site. A water source on your land is not an authorized public water supply, and TCEQ issues those systems.
Start with the free data. In Texas the water board publishes all the drilling logs. Make a radius map around your site, download those logs, and see what results people have actually gotten at different depths.
A test well would run about $10,000 to $15,000. How much you can pull is normally proportional to the acreage you control, which is why some data center sites tie up far more land than the facility covers.
We do wells and raw water supply studies, and developers can start with the work we do for developers and builders.
What happens if you close without these answers?
The developer or campus owner pays. The carry runs while you wait on the utility, the city or TCEQ, and reviews slow down when requirements are unclear.
If the utility lacks capacity, you are looking at a developer funded upgrade that may cover legal, engineering and construction costs. It could be a different supply path. It could be a private system nobody budgeted.
Each one is worth pricing before you close. One thing to do this week: ask the utility in writing for capacity in LUEs or gallons per day by phase, and the source behind it. Do not let the land go hard until that answer is on paper.
Watch the full episode
The full episode is on YouTube: https://www.youtube.com/watch?v=DiTwtx_U9w8 (opens in a new tab)
Frequently asked questions
How much water does a data center need per day?
It depends largely on how you cool the facility. You state demand in gallons per day by phase, then convert to LUEs using about 250 gallons per day per home.
Is a letter from the utility enough proof of water?
No. Ask for capacity by phase, the wholesale contract it relies on, and any storage or pump project that is actually on a docket.
Can I just drill a well on the site for water?
A water source on your land is not an authorized public water supply. TCEQ issues those systems, and groundwater conservation districts set the rules.
What water loss number should a utility have?
The benchmark we use is 10%. One small Texas utility has lost 45% of its water for five to six years, so ask for recent numbers.
Where can the wastewater from the site go?
Options include septic, an on-site 210 authorization, or a lift station pumping to the city main. A pending permit is not an issued one.
What does a test well cost?
About $10,000 to $15,000. Before that, check the state drilling logs around your site for what people actually got at different depths.
Related resources
- Prove the water before you close: what a Texas data center site can really supply
- Texas data center water supply: what developers are getting wrong before they break ground
- Data center water supply in Texas: how to build a water plan that holds up
- Can treated wastewater cool a Texas data center? How to cut potable demand and plan the blowdown
Is your Texas data center site missing one of the three answers?
We do water and wastewater feasibility, wells and raw water supply studies, and TCEQ permitting for Texas sites. Send us your phasing and we will look at water and wastewater against it before you commit.
Next step: tell us about your site. An engineer reads every message and gives you a first answer.
Keep reading
More to read
- Who designs package wastewater treatment plants for new subdivisions in Texas?
- Which engineers help industrial warehouse developers with water and sewer for sites in a Texas ETJ?
- Can we put an easement on national park land?
- A kiosk label or a vending machine label: the word that decides your permit schedule
What we do
On this page
- Why does the land deal move faster than the water answer?
- What proof should you have in hand before you close?
- What does a capacity letter leave out?
- How do you check whether the utility is reliable?
- If the utility cannot serve you, can your own well carry the load?
- What happens if you close without these answers?
- Watch the full episode
- Frequently asked questions
- Related resources
- Is your Texas data center site missing one of the three answers?
Planning a project?
Get a feasibility reviewTalk to an engineer
Tell us about your project
An engineer reads it
Not a salesperson. Someone who can tell you whether the pathway is real.
You get a first answer
Your options, the agencies involved and the questions that decide cost and schedule.
You decide
No commitment to have the first call.
Prefer the phone? (214) 833-6748