Can we put an easement on national park land?

You cannot record an easement on national park land, because the Park Service issues a revocable right-of-way permit instead and sets its own terms.

Not as a recorded easement. The Park Service does not convey an easement interest for a utility crossing, so an easement on national park land is not the instrument your utility will end up holding. What it issues is a discretionary, revocable right-of-way permit, and that permit carries conditions a recorded easement never does.

Project photo: an aerial view of a water main during construction

Why can't a utility record an easement across park land?

Because the Park Service authorizes use of the land, not an interest in it. The Park Service rights-of-way rule at 36 CFR Part 14 (opens in a new tab) defines a right-of-way permit as a discretionary and revocable special use permit, then states what the permit is not: it "does not grant, convey, or imply transfer of title to any interest in, including a leasehold or easement interest in, the lands or waters authorized for use."

That one sentence explains most of the confusion on these projects. Your title work assumes a permanent right that runs with the land. A park crossing hands you a permit that can be conditioned and that the agency can end, so the line, the funding plan and the rate impact all get planned around a right you do not own.

What does the Park Service issue instead?

A permit that lets a utility pass over, under or through Park Service land. The Park Service's rights-of-way manual (opens in a new tab) describes the instrument as a permit issued to a third party to pass over, under, or through an NPS-owned or controlled area. It also names the facilities a permit may authorize, including common utilities such as fiber, water, and power lines.

Read the manual as guidance, not as the rule. Its front matter states that the contents "do not have the force and effect of law." The binding text is 36 CFR Part 14; the manual is where the agency explains how it applies that text.

How does a park crossing application start?

With the superintendent of the affected park unit, before any form. The rule asks a potential applicant to contact the superintendent to schedule a pre-application meeting about the project, the permitting process and the law and policy that apply. That meeting is also where the Park Service may say what makes an application complete, and give an expected timeline and potential costs the agency will incur to review and process it.

Then the paperwork. An application goes to the superintendent on Standard Form 299, with the materials the rule requires. A complete package starts review; it does not promise a permit. The rule says the Park Service "will not begin processing a right-of-way permit application" until it decides the applicant has complied, and that its determination "does not guarantee the NPS will issue a right-of-way permit."

What has to be in the application?

More than a route line drawn on an aerial. For a water or sewer crossing, these items decide how much submittal work the project takes:

  • A map that meets current NPS mapping standards, showing the proposed permit area, the placement of the proposed infrastructure, and the proposed access points and routes. The NPS may also require an official land survey, legal description, and digital information.
  • Proof of a valid water right from the appropriate state official or state law, for an application to operate and maintain infrastructure that supports the storage, diversion, conveyance, or use of water.
  • Access limited to existing roads, or existing or NPS-approved routes, trails, or access points. The NPS will not authorize new roads by a right-of-way permit.
  • Infrastructure designed to accommodate co-location to the greatest extent possible, plus a showing that the applicant evaluated all options for co-location with existing infrastructure.
  • Financial assurance and liability insurance, where the NPS decides the proposed project warrants them.

Can the Park Service say no, or end the permit later?

Yes to both, and the rule does not soften it. A permit issues only if the proposed use is "not incompatible with the public interest and consistent with applicable laws and policies." No right of access is granted under a right-of-way permit, and "Access routes and means of access identified in a right-of-way permit are revocable at the discretion of the NPS."

Design for the permit ending, not only for approval. A crossing that carries the only feed into a service area is a single point of failure in a document as well as in the ground. Where the permit is the only route, the contingency for losing it belongs in the project scope from the first draft, not added after the pre-application meeting.

What is the preservation easement the Park Service requires?

A different instrument that points the other way. A recipient of a Historic Preservation Fund grant for a development project must sign a preservation covenant or easement with the State Historic Preservation Office or an approved nonprofit, and it is recorded with the property title. That is the landowner giving protection to someone else, not a utility gaining a right to cross. The requirement is set out on the Park Service's page on preservation easements and covenants (opens in a new tab).

The term follows the grant, not the utility. It is based on the amount of federal grant funds the property received, so no two are identical. When a Park Service document uses the word easement, check which side of the transaction it sits on before you treat it as your utility right.

How is a Texas utility easement different?

In Texas the utility usually holds a recorded property right, and that is routine. Take TCEQ's sanitary control easement form (opens in a new tab). The form states that the easement permits the construction of homes or buildings upon the Grantor's property, and farming and ranching operations, as long as the restrictions in the form are followed. That is an interest recorded against the land, which is exactly what a Park Service permit is not.

Two files, two reviewers. On a Texas development, that easement work sits inside site civil and land development in Texas, next to the line's route and connection point, and it is the same groundwork behind securing water and sewer for a new community. A park crossing swaps the deed exhibit for a permit file, reviewed by a superintendent rather than a county clerk.

Is the crossing ready to file?

Run this list before the pre-application meeting, not after it. Utilities and municipalities can answer most of it from records they already hold.

  1. The park unit is identified, with the superintendent's office that would process the application.
  2. The pre-application meeting is held or scheduled.
  3. A valid state water right is documented for the water the infrastructure conveys.
  4. The route stays on existing roads and approved access points, with no new road proposed.
  5. Co-location with existing infrastructure is evaluated and documented.
  6. The map meets current NPS mapping standards, and the survey question is settled.
  7. Review costs, financial assurance and liability insurance the agency may require are in the project budget.
  8. A contingency exists for operating if the permit is revoked.

The crossing is ready to file only when every item answers yes. An item that answers no is a question for the pre-application meeting, which costs less than a returned application.

Scope and limits. This is general education on the federal right-of-way process for a utility crossing Park Service land, based on the rule and the agency guidance as published. It is not legal advice, it is not a permit strategy for a specific crossing, and it does not cover state park systems, tribal land or other federal agencies, which run their own processes. Route and design decisions stay with the Park Service and your project team.

Frequently asked questions

Can a water line cross a national park?

It can, under a right-of-way permit. The Park Service's rights-of-way manual names water lines among the utilities a permit may authorize, and the decision is made for the affected park unit.

Does a right-of-way permit give the utility any land interest?

No. The rule states that the permit does not grant, convey, or imply transfer of title to any interest in the land, including a leasehold or easement interest.

Who do we contact first about crossing park land?

The superintendent of the park unit the project would affect. The rule asks a potential applicant to schedule a pre-application meeting before submitting an application.

How long does a Park Service right-of-way permit take?

The rule sets no fixed review period. It says the Park Service may give an expected timeline and potential costs at the pre-application meeting, so ask for both while you are there.

Is a preservation easement the same as a utility easement?

No. A preservation covenant or easement protects a historic property and is required as a condition of a Historic Preservation Fund grant. It is held by the State Historic Preservation Office or an approved nonprofit, not by the utility.

Can the Park Service require proof of our water right?

Yes. An application to operate and maintain infrastructure that supports the storage, diversion, conveyance, or use of water must include proof of a valid water right from the state.

Need to cross federal land with a water line?

MES designs water and wastewater lines and the easement and permit documents that go with them, and we tell you early when a route depends on a revocable permit instead of a deed.

Ask for the first step: funding-readiness package for one named program window. A program-fit check, a principal-forgiveness screen and the scope, cost estimate and engineering report the program asks for (Timed to the program deadline). Ask for it here.

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.