Blog

Will water and sewer reach your Texas tract before you close? Here is how to find out

You find out by getting the answer in writing from the utility that holds the service rights, before you sign. A nearby water line is not service. A well log from a neighbor is not your well. Mike opened the show with a 12 acre flex commercial site in Denton County, Texas where the developer had a water line in front of the property and was quoted about $700,000 for the connection, a number he had not budgeted. That gap is what this episode is about. Here is how we screen a tract, what to ask for, and what to treat as unconfirmed.

Project photo: a water main during construction

Can a utility sell me water it does not have the rights to?

No. A utility can only sell what its water rights support. Aquifer yield, purchased water from neighbors, or a combination, the total is capped.

Anything is possible, Mike said. The utility can buy more water from an adjacent provider, but that comes at a cost, and that cost can land on you.

The certificate of convenience and necessity, the CCN, is the mapped service area the Public Utility Commission regulates for water and sewer. The maps are public online.

That matters because the CCN holder has the first right to serve your development, and under its bylaws it is required to serve you.

If you want to self serve instead, rainwater harvesting, a groundwater well or your own wastewater plant are options, but you may have to show the utility's system is prohibitive for you.

We often start this screen before any money is spent. If you are still deciding where to buy, it helps to see how we check water and wastewater service before a tract is committed early.

How do I screen a tract before I pay for engineering?

Work in this order: water supply, then the utility, then sewer. Each step is cheap and each can end the deal before you spend more.

Groundwater first. Pull the Texas Water Development Board records for wells near the site. You can see how deep they are and what they yield. The permits list the driller, so call one or two and ask what they think of your site and what it would cost.

Then look at the utility. The state publishes annual spreadsheets on each utility's water rights, water loss and how much water is actually used. A spot check there tells you whether a paid capacity study is worth ordering at all.

Then call the utility about the lines in front of the property. Sewer is usually the expensive one: a lift station and force main to their collection line, or an extension of that line to your site. Many developers form a municipal utility district and build their own plant, especially where a discharge permit to a river is possible.

What did two field checks change about a site?

They changed the answer, and both are easy to skip.

The first is a well's history. Mike described a well next to a site that was 30 feet deep and made a very high yield when drilled. Five years later, in a drought, it was pumping about 50 gallons per minute. That changes your view of the site. Check yields across wet years and dry years before you trust a well log.

The second is wastewater capacity. Look at the plant's permitted capacity against actual flow. Monthly or quarterly data on the EPA's ECHO site shows the trend. One case: a city plant with no room to expand and no money to fund it. The path there was a master meter and a wholesale agreement, negotiated.

A well log is one day. A wholesale deal has to be negotiated. Wholesale means you own the collection system inside your site and the utility meters one connection and bills you. In Texas the water and sewer utilities are often different agencies.

Who pays the utility fees, and when?

The developer pays first, and most of it before closing. These are upfront fees, separate from engineering fees, and they land on a cash constrained buyer.

One municipality required its own meter, a backflow preventer and $50,000. That can come due before entitlements are in hand.

That is a real problem for construction loans. A lender may not release funds until the water company signs off, and the water company may not sign off until the fee is paid.

The landowner feels it too. The slide put it plainly: a buyer who finds the service gap reprices or walks. Of the 35 Texas developer companies we have spoken with since April 2026, 17 had that same reaction to the fees.

On the permitting side of a site, driveway permits and trip generation letters in Texas are a separate gate we handle alongside the utility questions. If your business is building lots, our work with developers and builders starts with this same due diligence.

What should I get in writing before I close?

Get it in writing from the CCN holder, and treat a verbal answer or a feasibility letter as unconfirmed.

Ask for four things: how many land use equivalents the utility can commit, what water source backs them, where the wastewater goes, and the fees, meter and tap requirements. One land use equivalent equals one single family home. Commercial sites take some calculation.

Ask whether you install and dedicate the lines or the utility builds them. Mike has seen both.

Know your fallback before you need it: a well, a wholesale agreement, a release from the CCN, rainwater, or your own wastewater plant. If the prices are too high for your development to support, the fallback is what keeps it alive.

A feasibility letter is a starting point, not a commitment. The utility pays an in house or third party engineer to produce it, and Mike has seen those cost $1,000 to $7,000, with one complicated analysis at $45,000.

Watch the full episode

The full episode is on YouTube: https://www.youtube.com/watch?v=_Ds9va00nmc (opens in a new tab)

Frequently asked questions

Does a water line in front of my property mean I can connect?

No. The utility holding the service rights decides service, and the cost can be far beyond what the line suggests. One site was quoted about $700,000.

How much does a feasibility letter from a utility cost?

Mike has seen them run $1,000 to $7,000. One complicated analysis reached $45,000.

Can I use a well instead of the utility?

Possibly. Check nearby well records and their yields in dry years, then ask a driller. You may have to show the utility's system is prohibitive for you.

What is a wholesale wastewater agreement?

You own the collection system on your site, and the utility bills one metered connection. It has to be negotiated.

Can a low yield in a dry year sink my site?

It can change the answer. One well made a very high yield when drilled and about 50 gallons per minute in a drought five years later.

When do I find out about the fees?

During due diligence, hopefully before you close. Ask the CCN holder in writing, and treat a verbal answer as unconfirmed.

Does your Texas tract have service in writing?

We screen water supply, the utility and sewer for Texas tracts, then help you get the capacity answer and fees in writing before you commit. If the utility answer does not hold up, we help you find the fallback.

Next step: tell us about your site. An engineer reads every message and gives you a first answer.

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.