Concrete wall forms and rebar beside a deep excavation, with a small dark metal building and dry hills behind.

Project

Replacement 40,000 gpd wastewater plant for a growing RV park

A growing RV park in Colorado replaced its aging wastewater system with a 40,000 gpd plant designed to its effluent limits.

Wall forms for the new treatment plant during construction, Colorado, August 2024.

The problem

An RV park in Colorado was growing. Its aging wastewater treatment system could no longer handle the demand or meet updated discharge requirements.

The replacement plant had to carry the higher flows and meet effluent limits: BOD of 5 mg/L, TSS of 1 mg/L and total inorganic nitrogen (TIN) of 80 mg/L.

The pathway

MES led the civil design for a new treatment plant sized for 40,000 gallons per day.

MES developed the engineering plans and technical specifications for the plant to meet regulatory standards.

MES also designed the site layout. It covered grading, drainage and the utilities that serve the new plant and keep the park running.

During construction, MES worked closely with the construction team. The team answered design questions and gave technical support throughout the build.

In August 2024 the plant's concrete walls were going up, with wall forms and rebar set beside a deep excavation.

In 2025 MES prepared the as-built drawings for the finished work.

The result

The replacement plant is complete. It was built to carry the park's higher flows and designed to its effluent limits.

MES stayed with the project from design through construction, and the as-built drawings record what was built.

Design flow
40,000 gallons per day
BOD limit
5 mg/L
TSS limit
1 mg/L
TIN limit
80 mg/L
Closeout
As-built drawings, 2025
  • Wastewater treatment plant
  • Civil site design
  • Construction support

More projects

Other work like this

See all projects

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.