Lined wastewater lagoon beside a dirt access road, with a small red building and hills under a clear sky

Project

Town of Oak Creek I&I and water loss analysis

MES quantified water loss and I&I for the town, delivered the study report with engineering estimates and a prioritized roadmap in 2024 and a revised I&I report in 2025; follow-up work continues in 2026.

Wastewater lagoon, Oak Creek, Colorado

The problem

The Town of Oak Creek, Colorado had aging water distribution and wastewater collection systems.

Water loss in the distribution system was unquantified. So was the infiltration and inflow (I&I) in the collection system.

The pathway

The work has run in three phases.

The first phase was a study in 2024. MES assessed the age and condition of both systems.

MES analyzed water loss in the distribution system, quantified it and outlined its causes. MES also identified and quantified the I&I in the wastewater collection system.

MES prepared a budget estimate for replacing critical infrastructure components, so the town could plan and prioritize future upgrades within its financial limits.

The second phase was a follow-up. MES made site visits in December 2024 and April 2025.

In April and May 2025, MES reviewed metered and unmetered addresses, checked metered addresses against the county map, and added second meter reads and total flow.

MES prepared an I&I report in July 2025 and revised the study to address review comments in August 2025.

From late August to September 2025, MES reviewed CCTV and matched sewer manholes between the records and a spreadsheet.

The third phase is under way. In March 2026, MES worked on a Class 5 planning level cost estimate for wastewater treatment plant improvements.

From July to October 2026, MES worked on further I&I updates, CCTV and manhole revisions. MES also worked on the design of the lift station that feeds the town's MBBR treatment plant.

The result

MES delivered the study report in 2024, with engineering estimates and a prioritized roadmap for future replacements and improvements, and a revised I&I report in 2025.

MES made recommendations to reduce I&I and water loss and to improve how both systems perform.

The 2026 work is still in progress.

Systems studied
Water distribution and wastewater collection
2024 study
Final report and replacement cost budget
2025 follow-up
Address and meter review; I&I report, July 2025, revised August 2025
Sewer records review
CCTV review and manhole record matching
2026 work, in progress
Class 5 WWTP cost estimate, I&I updates, design of the lift station feeding the MBBR plant
  • I&I study
  • Water loss analysis
  • Capital planning

Talk to an engineer

Tell us about your project

  1. An engineer reads it

    Not a salesperson. Someone who can tell you whether the pathway is real.

  2. You get a first answer

    Your options, the agencies involved and the questions that decide cost and schedule.

  3. You decide

    No commitment to have the first call.

Prefer the phone? (214) 833-6748

Site location, what you are trying to build, and your deadline.

Plans, a site map or photos: up to 5 files, 10 MB each.

Read our privacy policy.